DANS cost model

Testing

  • To move back and is due end of May 2013 - as deliverable has been split into two

4C project

  • HT working on 4C project which kicks off mid Feb

Mapping exercise

  • Can only carry this out at high level as costs are not easily apportioned across the headings given in the ISO

Test data from DP4lib

  • The DANS model relates to indirect costs which are apportioned across the direct costs this menas that it is difficutlt to use the test data
  • There is no problem with the direct costs
  • KK requested that the template be completed for this exercise so that we can report on this in the second deliverable